Bescom loses 16,749 transformers in seven months

The Hindu NationalBy The Hindu National
16 Sept 2026
Original: English
Bescom loses 16,749 transformers in seven months
Bescom loses 16,749 transformers in seven months
Visual Coverage
AI Synopsis & Key Briefing

The power utility lost around 40,000 transformers each year since 2023 to overload, lightning, aging, short circuits and manufacturing defects

Key Highlights & Official Takeaways
  • The power utility lost around 40,000 transformers each year since 2023 to overload, lightning, aging, short circuits and manufacturing defects
  • Of this, ₹2,41.04 crore was for replacement of distribution transformers.
  • Officials state that on an average, around 28,000 transformers are added every year to the existing number.
  • The average percentage of failure of transformers has remained consistent between 7 and 8% since 2019.
Comprehensive News & Policy Report

Every year, around 38,000 to 40,000 transformers are burnt or damaged due to overload, lightning, aging, short circuits, manufacturing defects and other reasons within the jurisdiction of the Bangalore Electricity Supply Company Ltd.

(Bescom). This year, in just seven months, around 16,749 transformers were burnt in Bescom jurisdiction until July 2026 out of a total of 5,71,178 According to Bescom’s Annual Performance Review report (APR), it incurred capital expenditure of ₹3,164.79 crore for the financial year 2024-25.

Of this, ₹2,41.04 crore was for replacement of distribution transformers. Officials state that on an average, around 28,000 transformers are added every year to the existing number. The average percentage of failure of transformers has remained consistent between 7 and 8% since 2019.

A Bescom official acknowledged that despite regular service and maintenance, transformers get damaged due to overloading and lightning. The official said: “We have identified a few places where overload happens and necessary steps are being taken.

We have installed additional transformers and upgraded existing transformers to avoid overloading issues.” He added: “Phase balancing process is followed. Regular maintenance of transformers, cable management, tightening of connections, and strengthening of damaged earthings are carried out regularly.

Cutting trees along high tension and low tension routes to avoid tree branches touching electric wires or even transformers is also done. We have also tightened loose paths, straightened crooked poles, and removed unauthorised loads.” As per the APR report, the failed transformers are being replaced with repaired transformers from the buffer stock.

The report further stated that the replacement of failed distribution transformers is essential to maintain continuous power supply for drinking water installations and maintain quality power supply to consumers. Bescom said there is a sufficient buffer stock of 10,202 new and repaired transformers at transformer banks and divisional stores for replacement of failed ones.

The replacement or installation cost of a standard distribution transformer averages around ₹5.05 lakh per unit. It varies according to the procurement, contract prices and is based on the capacity including 25kVA, 500kVA, and 1000kVA.

M.G. Prabhakar, energy expert, said: “Technologies have vastly improved in manufacturing of transformers and the State government must purchase top class ones. Whenever they are purchased in huge numbers, the stock should be double-checked so that there are no faulty ones.

If there is an overload issue, naturally they fail. But Escoms must ensure they are not overloaded. Whenever a particular power capacity requires augmentation, they must install more than one transformer in such places.”

Actionable Steps for Aspirants & Citizens
  • Aspirants and citizens are advised to monitor official notices and circulars issued by The Hindu National.
  • Verify all prescribed eligibility criteria, cutoff dates, and authenticated document requirements prior to formal submissions.
  • Track connected examination timetables, vacancy advisories, and administrative gazettes on SuchnaSetu.
Official Notice Specification
Issuing AuthorityThe Hindu National
Topic CategoryINDIA
JurisdictionAll India / National
Publication Date16 September 2026
Connected Government Jobs & Upcoming Exams