Bombay High Court puts road project on hold till State files report on mangrove loss, compensatory measures
The Bombay High Court directed the State to submit figures documenting tree cover, losses, and five-year survival rates before any orders are passed
- ✓The Bombay High Court directed the State to submit figures documenting tree cover, losses, and five-year survival rates before any orders are passed
- ✓A 2018 High Court ruling mandated court approval for developments affecting wetlands.
- ✓Though the project will not require clearing mangroves, it impacts six trees, necessitating the planting of 100 trees as compensation.
- ✓Stating that it does not oppose the project but will not proceed without full compliance, the Court posted the matter to November 30.
The Bombay High Court has withheld permission for a road project in Mumbai until the State government submits a detailed report on measures taken to compensate for the loss of mangroves. The court also stated that ‘afforestation’ efforts must be completed before seeking clearances and that the process should not be treated as a mere formality.
A Bench comprising Chief Justice Mahesh C. Tripathi and Justice Advait Sethna made these remarks while hearing a plea by the Mumbai Metropolitan Region Development Authority (MMRDA) seeking permission to divert 0.2869 hectares of mangrove land in the Bandra-Kurla Complex area to construct an Automated Rapid Transit System covering 8.85 km.
A 2018 High Court ruling mandated court approval for developments affecting wetlands. Though the project will not require clearing mangroves, it impacts six trees, necessitating the planting of 100 trees as compensation.
Advocate Saket Mone, representing the MMRDA, argued that the Automated Rapid Transit System fulfills key connectivity needs. He added that tree planting falls under the jurisdiction of the Forest Department. In response, the Bench questioned why officials had not initiated remedial action when conceptualising the project.
Advocate General of Maharashtra Milind Sathe attributed the planting delays to a shortage of saline land, noting that saplings must be planted before the monsoon to ensure survival. However, the Bench pointed out a gap between regulators’ filings and ground reality, questioning how authorities could grant permission when rules mandate 30% tree cover.
The Court directed the State to submit figures documenting tree cover, losses, and five-year survival rates before any orders are passed. Stating that it does not oppose the project but will not proceed without full compliance, the Court posted the matter to November 30.
Mr. Mone was briefed by advocate Fatema Ansari, while Mr. Sathe was briefed by Government Pleader Onkar Chandurkar.
- •Aspirants and citizens are advised to monitor official notices and circulars issued by The Hindu National.
- •Verify all prescribed eligibility criteria, cutoff dates, and authenticated document requirements prior to formal submissions.
- •Track connected examination timetables, vacancy advisories, and administrative gazettes on SuchnaSetu.
| Issuing Authority | The Hindu National |
|---|---|
| Topic Category | GOVERNANCE |
| Jurisdiction | All India / National |
| Publication Date | 27 November 2026 |