JCBs roll in, hundreds up in arms: Mumbai’s Prabhadevi chawl demolition drive begins

10971145 Prabhadevi chawl demolition drive
- ✓10971145 Prabhadevi chawl demolition drive
- ✓The Mumbai chawl demolition drive was scheduled to start at 10 am.
- ✓32-L and 33-L, at the southern end of Prabhadevi station on its western side.
- ✓According to railway records, the process began in February 2022, when officials conducted a survey and issued show-cause notices to the occupants.
As JCBs arrived at the Prabhadevi chawl in Mumbai on Friday, November 20, to carry out the Western Railway’s demolition drive on the encroached land, hundreds gathered in protest, surrounding the police personnel and the machines, preventing railway staff from undertaking the demolition.
The demolition drive was scheduled for Thursday, November 19, but was postponed to Friday after the occupants of the affected structures approached the Bombay High Court. The Mumbai chawl demolition drive was scheduled to start at 10 am.
Anticipating protests, the authorities deployed dozens of police personnel to maintain law and order. On Thursday, a bench of Chief Justice Mahesh Chandra Tripathi and Justice Advait M Sethna of the Bombay HC briefly heard a batch of petitions on the Mumbai chawl demolition drive, seeking rehabilitation for persons affected by the action.
Advocate Prakash Ambedkar, appearing for some petitioners, told the bench that no demolition could take place without resettlement or rehabilitation. He added that the state government had assured alternative accommodation to slum dwellers.
The Railways' lawyer, however, argued that the petitioners were unauthorised occupants and could file appeals before the appropriate forum or competent authority to raise their grievances. The lawyer also said the rehabilitation matter would be dealt with by another bench having the relevant assignment, following which the HC asked the petitioners' lawyer to take appropriate steps.
The demolition concerns railway land near Chawl Nos. 32-L and 33-L, at the southern end of Prabhadevi station on its western side. The proposed action follows a four-year-long legal process to reclaim the land, which the Railways plans to use to construct staff quarters.
According to railway records, the process began in February 2022, when officials conducted a survey and issued show-cause notices to the occupants. Following hearings and final arguments, the Estate Officer issued eviction orders in October 2026, directing the occupants to vacate the premises.
It also warned that the Railways can proceed with demolition and recover the expenses incurred from the occupants in case of non-compliance. Meanwhile, the demolition drive has triggered concerns among residents, with several claiming that their families have lived in the locality for 50 to 60 years.
- •Aspirants and citizens are advised to monitor official notices and circulars issued by Maharashtra State Bureau (Mumbai).
- •Verify all prescribed eligibility criteria, cutoff dates, and authenticated document requirements prior to formal submissions.
- •Track connected examination timetables, vacancy advisories, and administrative gazettes on SuchnaSetu.
| Issuing Authority | Maharashtra State Bureau (Mumbai) |
|---|---|
| Topic Category | GOVERNANCE |
| Jurisdiction | MH State |
| Publication Date | 20 November 2026 |