MCD works against legal hurdles to clear Ghazipur landfill, meet 2027 deadline

Delhi NCR Civic & GovernanceBy Mishal Mussaddique
23 Nov 2026
Original: English
MCD works against legal hurdles to clear Ghazipur landfill, meet 2027 deadline
MCD works against legal hurdles to clear Ghazipur landfill, meet 2027 deadline
Visual Coverage
AI Synopsis & Key Briefing

10975479 ghazipur landfill

Key Highlights & Official Takeaways
  • ✓10975479 ghazipur landfill
  • ✓According to government data released in October, at Ghazipur, 69 lakh Metric Tonnes (MT) of legacy waste was still left to be cleared.
  • ✓The Rs 249-crore project for the third phase of biomining and reclamation of the land was awarded to the agency, which was the lowest bidder.
  • ✓This does not, however, take into account the nearly 3,000 MT of fresh waste being deposited at the site daily.
Comprehensive News & Policy Report

The Municipal Corporation of Delhi (MCD) is currently navigating a Supreme Court order on stay on a tender owing to which work on the third phase of biomining operations at the Ghazipur landfill site is on hold. According to government data released in October, at Ghazipur, 69 lakh Metric Tonnes (MT) of legacy waste was still left to be cleared.

According to a report published by the Commission for Air Quality Management (CAQM) on Sunday, the progress in legacy waste processing at Ghazipur is the slowest among all major landfill sites in Delhi, with the commission rating it ‘unsatisfactory’.

The Supreme Court had last month stayed the tender for the work at the site, awarded to Greentech Environ Management. The Rs 249-crore project for the third phase of biomining and reclamation of the land was awarded to the agency, which was the lowest bidder.

The Standing Committee of the MCD had also approved awarding of the tender at a meeting held last week. The tender was issued last year. Greentech appeared before the Delhi High Court to be included in the financial bids as the agency was earlier disqualified after being blacklisted by the Municipal Corporation of Gurugram (MCG) and fined over Rs 5 crore for failing to meet processing targets last year.

The high court eventually allowed Greentech to bid for the tender. However, Guru Ramdas Constructions, the second lowest bidder for the tender, moved the Supreme Court in October challenging the HC’s decision, after which the apex court issued a stay on all orders until a judgement was passed.

This meant that Greentech could not start their operations at the site. The Delhi government then moved the court to vacate the stay order. The Supreme Court was supposed to hear the matter on Monday, but it did not take it up and postponed it by a week.

According to MCD sources, however, the December 2027 deadline will not be missed even after the court stay as Alwazo Solutions JV, another agency which was awarded the tender for the second phase of the biomining work at Ghazipur, is currently carrying out work at the site on an interim basis — despite its contract having been terminated in December 2024 for failing to meet the processing targets.

According to the recent CAQM report, against an annual target of 39.12 lakh MT as of October 31, only 16.53 lakh MT legacy waste was processed at the Ghazipur landfill — an achievement of 42%, fetching a rating of ‘unsatisfactory’.

This does not, however, take into account the nearly 3,000 MT of fresh waste being deposited at the site daily. Landfill sites at Okhla and Bhalswa, meanwhile, have met 67% and 57% of their targets, respectively. The three sites in Delhi had a combined target of 114.99 lakh MT of legacy waste liquidation for 2026.

Collectively, the three sites have processed 62.28 lakh MT, leaving a gap of 52.71 lakh MT.

Actionable Steps for Aspirants & Citizens
  • •Aspirants and citizens are advised to monitor official notices and circulars issued by Delhi NCR Civic & Governance.
  • •Verify all prescribed eligibility criteria, cutoff dates, and authenticated document requirements prior to formal submissions.
  • •Track connected examination timetables, vacancy advisories, and administrative gazettes on SuchnaSetu.
Official Notice Specification
Issuing AuthorityDelhi NCR Civic & Governance
Topic CategorySTATES
JurisdictionDL State
Publication Date23 November 2026
Connected Government Jobs & Upcoming Exams
Active on SuchnaSetu
Official Source Attribution: Delhi NCR Civic & Governance
View Publisher Source Link

SuchnaSetu provides verified civic and public policy reports based on official notices. Primary publication and copyright remain with the respective government authority or publisher.